Earned Value Management
TMS

Earned Value by Control Account

The Overview grid rolls BAC, BCWS, BCWP, ACWP, CV, SV, CPI, SPI, EAC and VAC from each work package up through control accounts and the WBS, cumulative or current period.

Earned Value by Control Account

EIA-748-Aligned Structure

Control accounts sit at the intersection of the WBS and OBS, with work packages carrying the earned value method, so a plan is organized the way EIA-748 expects from the start.

Performance Measurement Baseline

Capture the baseline that earned value measures against, replace it when the plan is re-baselined, or compose one from actual cost through a period boundary plus the forward plan.

Performance Measurement Baseline

Bottom-Up EAC

EAC is actual cost to date plus an estimate to complete rebuilt from the remaining labor and non-labor plan, so VAC reflects the plan you are actually executing, not a formula.

Bottom-Up EAC

Earned Value Methods per Work Package

Each work package declares how it earns value, Percent Complete or Level of Effort, and ProjectXL warns when a work package has no method or lacks the baseline LOE needs.

Earned Value Methods per Work Package